Connection capacity, contracted power and measured demand.

The unit may be the same, but the meaning is different.

Technical limits

Grid connection limits define the permitted scope of grid use and technical operating conditions. Increasing an EMS setting does not change the authorised grid connection. A fuse rating alone also does not describe all operating requirements.

Billing level

Contracted billing power is used under the applicable network tariff framework. Check its meaning and the consequences of changes against current rules and your metering point. Do not treat old tariff examples as universally valid.

Time-based measurement

Measured power may refer to an average over a specified interval, whereas a real-time reading may cover a different period. Short starting currents and interval demand peaks are not the same. Both perspectives may be needed for a sound decision.

Practical management

Before lowering contracted values, analyse several periods and planned future changes. Verify whether controls reliably limit demand without disrupting operations. Calculate the financial effect using current tariffs and rules.

Checklist