How does grid export limiting work?
Metering, control and device response must work together.
Measure at the correct point
Export control requires data at the connection point of the entire site. Measuring only at the inverter does not capture simultaneous demand from other devices. Meters, current-flow directions and communications must be configured correctly and checked during commissioning.
Control systems have response times
When consumption changes suddenly, the system needs time to adjust generation or charging. Network operator requirements and equipment response characteristics must be compatible. A zero-export setting does not in itself prove compliance during every transient.
When the battery is full
Storage is limited by power and available headroom. If it cannot accept more energy, the system must reduce generation or use permitted flexible demand. Economics should therefore also account for curtailed or lost generation.
Test at commissioning
Tests should cover a sudden load disconnection, a full battery and communication failure. Agree a safe failure mode. Monitor actual exports and events, not only the limits entered in an app.